Abstract
This Meta EIP lists the EIPs formally Proposed, Considered, Declined for & Scheduled for Inclusion in the Glamsterdam network upgrade.
Specification
Definitions for Scheduled for Inclusion
, Considered for Inclusion
, Declined for Inclusion
and Proposed for Inclusion
can be found in EIP-7723.
EIPs Scheduled for Inclusion
Considered for Inclusion
- EIP-7732: Enshrined Proposer-Builder Separation
- EIP-7782: Reduce Block Latency
- EIP-7805: Fork-choice enforced Inclusion Lists (FOCIL)
- EIP-7928: Block-Level Access Lists
Proposed for Inclusion
- EIP-6873: Preimage retention
- EIP-7667: Raise gas costs of hash functions
- EIP-7793: Conditional Transactions
- EIP-7819: SETDELEGATE instruction
- EIP-7843: SLOTNUM opcode
- EIP-7919: Pureth Meta
- EIP-5920: PAY opcode
- EIP-7791: GAS2ETH opcode
- EIP-7903: Remove Initcode Size Limit
- EIP-7907: Meter Contract Code Size And Increase Limit
- EIP-7923: Linear, Page-Based Memory Costing
Activation
Network Name | Activation Epoch | Activation Timestamp |
---|---|---|
Sepolia | ||
Holešky | ||
Mainnet |
Note: rows in the table above will be filled as activation times are decided by client teams.
Rationale
This Meta EIP provides a global view of all changes included in the Glamsterdam network upgrade, as well as links to full specification.
Security Considerations
None.